Northglen Orchard Public School
May 2, 2025
Contingency Planning: Northglen Orchard Public School
Hello everyone,
We are writing today to provide additional information about the updated timelines for building the new school. As we shared, while we will continue to work with the contractor to try and reduce delays wherever possible, at this time the updated timeline targets a building completion date of late November 2025. Students and staff would likely occupy the new school early in the new year.
The contingency plans outlined below have been developed to accommodate students and staff based on this revised schedule.
To allow for the least disruption for all students and staff within the school communities involved, Northglen Orchard Public School students and staff will be organized together as classes within nearby KPR schools, to be able to move together into the new school.
This will allow all classes to remain together as part of the move and keep students with the same teacher throughout the year. To accommodate this planning within available school space, students and staff will be grouped by grades within these three grade clusters:
- Junior Kindergarten to Grade 2 Northglen Orchard students will attend Charles Bowman Public School
- Grade 3 to 6 Northglen Orchard students will attend Harold Longworth Public School, and
- Grade 7 to 8 Northglen Orchard students will attend Clarington Intermediate SchoolÌý
(Note: Charles Bowman PS Grade 7 students will remain at Charles Bowman as that school transitions to JK to Grade 8)
Upon completion of the new school, students and staff will move to Northglen Orchard Public School.
Our child care partner in this project – Durham Region, is using this information to finalize their planning and communication with families. Further information on child care and before and after school program planning will be shared as soon as it’s available.
Transportation will be provided to students who reside more than 1.6 km from their designated school noted above, and parents can register their transportation request through the Opt-In process beginning May 2nd.
After completion of the new school, transportation will be provided as per board policy to students who reside more than 1.6 km from Northglen Orchard Public School. As part of the move to the new school, the Opt-In window will be reopened for families to finalize transportation prior to the first day at the new school.
We appreciate that families will have continued interest and questions as we move forward with our planning. We invite families to submit their questions to kpr_info@kprdsb.ca, and we will continue to provide regular updates to families directly, and at the dedicated Northglen Orchard Public School section of our website at .
Sincerely,
Sonal Gohil
Superintendent of Education
April 10, 2025
Construction Update: Northglen Orchard Public School
Hello everyone,
We continue to be very excited about the new Northglen Orchard Public School, which will help support our growing student population in the Clarington area.
We are writing today to provide an update on timelines for building the new school.
While the project continues to move forward, the extended winter and spring weather has resulted in construction delays to concrete, block work and other components of the school’s construction.
We will continue to work with the contractor to try and reduce delay wherever possible. At this time the updated timeline targets a building completion date of late November, 2025, with occupancy by students and staff likely early in the new year.
Board administration are working on finalizing a contingency plan to accommodate students and staff based on this revised date.Ìý We will share further information to the school community by the end of this month as these plans are completed.
We appreciate everyone’s patience and understanding as we complete this project which will benefit students and families for generations to come.Ìý
Sincerely,
Nina Jaiswal
Superintendent of Education: Student Achievement (Acting)
At the March 25, 2025 Board meeting, Trustees approved Northglen Orchard Public School as the name for the new school in the Northglen neighbourhood in Bowmanville.
Northglen Orchard Public School was the preferred name shortlisted by a joint community-board school naming committee, after review and consideration of over 70 submissions.
New Elementary School
The ºÃÉ«tv District School Board is pleased to be moving forward with construction of a new elementary school to serve students and families in the Northglen neighbourhood and surrounding Bowmanville area! The new school is an important step in addressing enrolment pressures in schools within the area.ÌýHighlights of the project include:
769 student spaces.
73 new licensed child-care spaces in four child-care rooms.Ìý
November 2024 Community Update
New School Boundaries
Attendance boundaries for the new Northglen neighbourhood school take effect with the opening of the school, which is planned for September 2025. It will open as a JK-Grade 7 school and then become JK-Grade 8 during its second year of operation.
Ìý
This interactive map illustrates the new school attendance area/boundary where families can look up their address to confirm whether they will attend the new school.
The new school boundaries will include some of the existing students from nearby schools, including Charles Bowman PS, Hampton Junior PS, M.J. Hobbs Sr PS and students from the Charles Bowman PS boundary attending Harold Longworth PS as a holding school.
For more information about theÌýcompleted boundary review, please click here.
Ìý
Sod Turning
KPR was pleased to be joined by provincial and municipal education partners to ceremoniously turn the sod on Friday, June 7, 2024Ìýat the construction site of the new Northglen neighbourhood school in Bowmanville.
The sod turning marks the official launch of the construction phase of this new, modern, fully accessible elementary school. Made possible through funding of over $36 million dollars, with an expected opening date of September 2025, the new school will have space for 769 students, from Junior Kindergarten to Grade 8, as well as a four-room childcare centre.Ìý
Child Care
Northglen Orchard Public School will include a child care centre for infants, toddlers and pre-school children and before and after school spaces for school aged children, operated by Durham Region. Families can register for care
Contact Us
ºÃÉ«tv District School Board
1994 Fisher Drive
Peterborough, ON K9J 6X6
Phone: 705-742-9773
Toll Free: 1-877-741-4577
Fax: 705-742-7801
Send an Email